By Month as of 01/26/2023
November 2022 | |
---|
1. Waiting for Building Permit | 100% Completed |
2. Construction fence installed | 100% Completed |
3. Start building pad | 100% Completed |
December 2022 | |
---|
1. Waiting on permit | 100% Completed |
2. Installing, water, sewer and storm drain | 100% Completed |
3. Construction fence installed | 100% Completed |
4. Completed Building pad | 100% Completed |
January 2023 | |
---|
1. Setting of cornerstone | 100% Completed |
2. Foundations started | 100% Completed |
3. Waiting on Electric and Plumbing permits | 100% Completed |
March 2023 | |
---|
1. Foundations completed and backfilled | 100% Completed |
2. Steel arrives on site | —0% Completed |
3. Underground electric and sound conduit installed | 100% Completed |
4. Underground electric and sound conduit and inspected | 100% Completed |
5. Underground plumbing installed | 100% Completed |
6. Underground plumbing inspected | 100% Completed |
7. Order Framing Materials | 100% Completed |
8. Order exterior Steel Doors | 100% Completed |
9. Install exterior Dens Glass | —0% Completed |
April 2023 | |
---|
1. Slab poured | —0% Completed |
2. Framing starts | —0% Completed |
3. Order store front entry Doors | 100% Completed |
4. Order windows | 100% Completed |
May 2023 | |
---|
1. Set Trusses | 0% Completed |
2. Framing completed and all bracing installed | 0% Completed |
3. Install exterior Dens Glass | 0% Completed |
4. Exterior doors and windows installed | 0% Completed |
5 Plumbing Rough in started | 0% Completed |
June 2023 | |
---|
1. Roof installed | 0% Completed |
2. Electric rough in started | 0% Completed |
3. Plumbing rough in completed and inspected | 0% Completed |
4. Exterior stone | 0% Completed |
5. HVAC rough in started | 0% Completed |
July 2023 | |
---|
1. Electric rough in completed and inspected | 0% Completed |
2. HVAC rough in completed and inspected | 0% Completed |
3. Insulation installed and inspected | 0% Completed |
4. Building cover up inspection completed | 0% Completed |
5. Start hanging drywall | 0% Completed |
6. Exterior EIFS completed | 0% Completed |
August 2023 | |
---|
1. Complete drywall | 0% Completed |
2. Complete painting | 0% Completed |
3. Interior doors and hardware installed | 0% Completed |
4. Suspended ceiling installed | 0% Completed |
5. Bath room flooring installed | 0% Completed |
6. Plumbing trim out completed and inspected | 0% Completed |
7. HVAC trim out completed and inspected | 0% Completed |
8. Exterior concrete completed | 0% Completed |
9. Soffit, Fascia and gutters installed | 0% Completed |
September 2023 | |
---|
1. Exterior site work completed | 0% Completed |
2. Restroom toilet partitions installed | 0% Completed |
3. Floor Covering Completed | 0% Completed |
4. Complete Punch List | 0% Completed |
5. Building Final Inspection | 0% Completed |
6. Training Sessions Completed with Church | 0% Completed |
7. Turn Building over to Church | 0% Completed |